Brisbane Convention & Exhibition Centre
Brisbane Convention & Exhibition Centre 309kW
Solar PV Owners Engineer
Feasibility, tender design, grid approvals and compliance engineer, for high profile inner city buiding.
Key Achievements:
- Detailed design for tender purposes, full drawing set.
- Owners engineer and contractor oversight.
- Post installation auditing and defect management.
- Grid application and management - Energex.
![](https://cdn.prod.website-files.com/63a12c43239f9dfa6b1a6228/63a389b4d8ccfb3ee96b176e_brisbane-convention.jpg)
Impact
![Technical design file of a solar and smart energy system.](https://cdn.prod.website-files.com/63a12c43239f9d41da1a6222/63a12c43239f9d42dd1a6258_commercial-design.jpg)
Project Scope
- Detailed design for tender purposes, full drawing set.
- Tender management and evaluation.
- Owners engineer, contractor oversight and post installation auditing.
- Grid application and management- Energex.
Project Details
- Detailed design for tender purposes, full drawing set.
- Tender management and evaluation.
- Owners engineer, contractor oversight and post installation auditing.
- Grid application and management- Energex.
![A man working on electrical schematics at an ergonomic desk](https://cdn.prod.website-files.com/63a12c43239f9d41da1a6222/64f6aaf317294453f65673fe_working-rana.jpg)
![A man working on solar panels on a roof](https://cdn.prod.website-files.com/63a12c43239f9d41da1a6222/63a12c43239f9da9e71a6257_commercial-compliant.jpg)
Project Challenges
- Utilising existing power distribution infrastructure and two remote distribution boards required for solar connection due to inaccessible MSB location.
- Existing power distribution board drawings and information were inaccurate.
- Building booked for 2 years in advance and a narrow installation window required.
- Architectural considerations.