Nillumbik Shire Council Landfill 4.99MW Solar Feasibility

Nillumbik Shire Council Landfill 4.99MW Solar Feasibility
  • Project: Nillumbik Shire Council Landfill 4.99MW Solar Feasibility

Enhar assessed the feasibility of two former landfill sites for the Nillumbik Shire Council.  Both sites were assessed as suitable. One site, at Plenty, was assessed as preferred. 

Enhar undertook market testing and liaised with the local grid distributor to arrive at an estimated cost.  Modelling of energy yields and life-cycle economics was performed.

The study was conducted in two stages.  A novel element involved assessing the suitability of rainwater collection from the solar panels.

Enhars Scope:

  • Feasibility and business case; Council and community investor modelling
  • Solar farm feasibility on landfill 
  • Project implementation steps
  • Presentations to council Strategic Leadership Team 

Project Details:

  • Multi MW solar farm project scoped up across multiple council owned properties
  • Review of former landfill sites 
  • Analysis of direct rainwater collection from PV panels
  • Ausnet connections to 22kV network
  • Multiple community groups with an interest in renewable energy

Project Challenges:

  • Identifying sites within the portfolio which are technically, environmentally and financially feasible 
  • Solar farm design on landfill which preserves the integrity of the cap
  • Consultation with wide range of internal and external stakeholders 